Much more Navarre Beach to enjoy

Keeping a protective watch for nesting sea turtles and birds, Weeks Marine Inc. is replenishing Navarre Beach with more than one million cubic yards of dredged sand in hopes of finishing by the holiday weekend of July Fourth.

The contractor has already placed about 150,000 cubic yards of sand in a project that started in the last week in April, nearly a month later than planned because Weeks was delayed in finishing work at other beaches. Still, good weather has helped work crews toward their goal of finishing within 50 days.

Read the full article in the May 19 issue of Navarre Press. Click HERE to subscribe online to your community newspaper.